Richmond Road – Client: London Square
Acting as Principal Contractor Phase Two Demolition of an 8-storey office block in Putney to make way for residential apartments
Location:
Putney SW15
Sector:
Residential Housing
Estimated Value:
£
Project Images:


About the project:
Sloane demolition was contracted for phase two of the works to deconstruct a 9storey concrete framed building to ground level.
Scaffold protection was required to all elevations to carry out top down demolition with two mini excavators. Each floor was back propped to engineers design to support demolition plant and machinery. Demolition was carried out successfully when reduced in height while abutting the new build concrete frame structure.
Project Challenges:
Due to a small footprint on site the use of 3.5ton excavators had to be used as the siting of the crane location could not permit heavier loads for the placement of the preferred machines.
Installation of protection screening, segregating off construction/demolition interface.
Noise and vibration had to be taken into consideration in respect of local restaurants close by.
Completion Date:
November 2014

Health & Safety
The Health, Safety & Welfare of our employees, others and the surrounding environment are of the utmost importance and essential to the efficient operation of our company.

Environmental
We take every care on site for plant and wildlife by ensuring a survey is carried out prior to commencement of work, by working closely with the appropriate authorities such as Natural England and alike, we ensure that plant life is undamaged and wildlife unharmed.

Quality Management
Sloane Demolition & Dismantling has implemented and maintains procedures and processes to ensure that all our legal and statutory responsibilities are understood and fully implemented.